Fortescue Metals Group Road Maintenance & Ore Loading

Nationwide Civil were engaged by FMG and Team45 to manage the first stage of the Iron Ore train loading process and maintain 70 km’s of heavy vehicle access road.

 

Project:                                      Fortescue Metals Group (FMG) Team45 Iron Ore Loading and Road Maintenance

Project Duration:                      January 2008 to July 2008

Project Value:                           $5.5 million

Client:                                       Fortescue Metals Group

Contact: (1)                               Mark Ivory:  0417 995 940

Position:                                    Planning and Scheduling Manager FMG

Contact: (2)                               Darren Ellis:  0438 688 420

Position:                                    Rolling Stock Manager Team45/FMG

 

Project Components


  • Management of the Iron Ore handling and Train loading 24 hours, 7 days a week
  • Works included up to 40 thousand tonnes per day loaded out
  • Major Plant Hire and Labour Supplier