S-Pit & U-Pit Levees Project
Nationwide Civil were engaged by Wesfarmers to construct the S-Pit & U-Pit Levees Project. Construction consisted of demolition of existing levees, removal of unsuitable material and reinstatement with selected and conditioned material to Level 1 DERM approval. Implications of an unsuccessful project would have included the mine ceasing operations for environmental reasons. This was a highly observed project and regarded as a great success, despite a record number and magnitude of rain events, including two cyclonic events, Nationwide Civil completed on time and without any disruption to the Clients mine operations.Project: S-Pit & U-Pit Levees Project
Project Duration: October 2010 to March 2011
Project Value: $5 million
Client: Wesfarmers Curragh - Blackwater
Contact: Mr Michael Mackintosh: 0407 175 936
Position: Delivery Manager
Project Components
- Clear and grub 2 Ha
- Strip topsoil 50,000m3
- Excavate to Spoil 260,000m3
- Condition and Borrow Material to Fill 380,000m3